== History ==
== History ==
Work began in [[1875]] with the foundation stone of the first pier laid on 4th June by the chairman of the Severn Bridge Railway, Mr Lucy.The work was completed in [[1879]].


'''Clutton Station''' was opened on 3rd September 1873 by the [http://en.wikipedia.org/wiki/Bristol_and_North_Somerset_Railway Bristol & North Somerset Railway]. Closed to passengers on 2nd November 1959 and goods on 15th June 1964.
The bridge was 4,162 foot (1,268 m) long, and 70 foot (21.3 m) above high water. The contractors for the construction of the metal portions of the bridge were Messrs. Hamilton's Windsor Iron Company of Liverpool, who also built [[w:Clevedon Pier|Clevedon Pier]]. The contractors for the railway and masonry portion of the bridge were Messrs. Vickers and Cook, London.


The station site is currently (2005) in use by A.R.M. Contractors Ltd who are specialists in railway demolition, dismantling and construction. Amongst other things they supply sleepers to preserved railways. I'd like to thank the owner of A.R.M., Garry Turner, for his help and friendly enthusiasm during my visit. I can thoroughly recommend his company to anyone in the preservation movement who is looking for supplies. Email me for a phone number.
On 25 October [[1960]], two barges, the Arkendale and the Wastdale, collided in heavy fog with one of the columns of the bridge, causing two spans to collapse. Part of the structure hit the barges, which were carrying petrol, setting fire to them. In addition, a 12 inch gas main which crossed the bridge from Sharpness to Lydney was also severed. Five people died in the incident. The bridge was deemed to be damaged beyond economic repair and was eventually dismantled in [[1970]], although several of the stone piers remain.
 
Photos taken during a downpour in July 2005. A HUGE thankyou to Nigel Callaghan for sending me copies of these pics after I lost them during a computer hardrive failure. His help is much appreciated. :)
 
== Images ==


== 1960s ==
<gallery>
Image:Severn Railway Bridge6.jpg|A 1966 view of the bridge taken from the north side of the river. ''&copy; John Thorn''
</gallery>
== 2004 ==
<gallery>
<gallery>
Image:clutton1.jpg|The remains of Clutton station looking in the direction of Bristol. Various bits of masonry still sit alongside the trackbed.
Image:Severn Railway Bridge1.jpg|The view of the remains of the Severn Railway Bridge as approached from the Sharpness end of the 16-mile [[w:Gloucester and Sharpness Canal|Gloucester & Sharpness Canal]].
Image:clutton2.jpg|Some rail is still visible onsite. This was the track that led to the goods yard.
Image:Severn Railway Bridge2.jpg|The eastern abutment of the bridge towers over the canal.
Image:clutton3.jpg|Standing at the southern extremity of the Clutton station site and looking north. The sleepers belong to A.R.M. contractors Ltd and were destined for the West Somerset Railway.
Image:Severn Railway Bridge3.jpg|The bridge was designed with a portion that could swing to allow larger boats passage along the canal. This is the pivot. The swinging section of bridge was built by Hamilton's Windsor Iron Works of Liverpool, who also built Clevedon Pier.  
Image:clutton4.jpg|Looking south across the station site. A weighbridge house is still standing behind the truck on the left. I did have pics, but I don't anymore!
Image:Severn Railway Bridge4.jpg|Looking across the River Severn and several large chunks of bridge are still lying in the mud.
Image:Severn Railway Bridge5.jpg|The course of the bridge as viewed from the Sharpness end of the canal. Several bumps in the river show the exact route the bridge took.
</gallery>
</gallery>
== External Links ==
[http://www.movietone.com/assets/BMN0627/quicktime/BMN_92745_32.mov Archive film of the demolition]


[[Category:Stations:Closed]]
[[Category:Bridges:Demolished]]
[[Category:Gloucester and Sharpness Canal]]
[[Category:John Thorn]]
[[Category:S&WR]]

Latest revision as of 20:04, 12 April 2026

To Lydney: Severn Bridge Station
To Sharpness: Sharpness

History

Work began in 1875 with the foundation stone of the first pier laid on 4th June by the chairman of the Severn Bridge Railway, Mr Lucy.The work was completed in 1879.

The bridge was 4,162 foot (1,268 m) long, and 70 foot (21.3 m) above high water. The contractors for the construction of the metal portions of the bridge were Messrs. Hamilton's Windsor Iron Company of Liverpool, who also built Clevedon Pier. The contractors for the railway and masonry portion of the bridge were Messrs. Vickers and Cook, London.

On 25 October 1960, two barges, the Arkendale and the Wastdale, collided in heavy fog with one of the columns of the bridge, causing two spans to collapse. Part of the structure hit the barges, which were carrying petrol, setting fire to them. In addition, a 12 inch gas main which crossed the bridge from Sharpness to Lydney was also severed. Five people died in the incident. The bridge was deemed to be damaged beyond economic repair and was eventually dismantled in 1970, although several of the stone piers remain.

1960s

2004

External Links

Archive film of the demolition